Your partner’s proposal named a functional lead, a technical lead and a project manager. It listed their day rates and their allocation. Then it said something like “client to provide subject matter experts as required.” That sentence is doing an enormous amount of work, and nobody has priced it.
The customer side of an ERP implementation team structure is the part every vendor is vaguest about, and it is also the part that most often decides whether the date holds. A partner can be excellent and still deliver late if the people who have to answer questions, approve designs and test the result are only available in the gaps between their day jobs.
This article names the seven roles you have to fill from your own organisation, what each one decides, what each one produces, and roughly how many hours a week it really takes.
Table of contents
The seven roles a customer has to fill
Executive sponsor
The sponsor decides the things nobody else is allowed to decide: whether a scope change is worth its cost, which department loses an argument about a shared process, and whether the project goes live on the date or moves.
They produce the decisions that unblock everyone else, and they produce them fast enough to matter.
The Project Management Institute’s in-depth Pulse of the Profession study on sponsorship found that an actively engaged executive sponsor is the top driver of project success, yet fewer than two-thirds of projects and programmes have one assigned at all.
The same study named three things that stop sponsors being effective: a culture that leaves them overextended, inefficient communication, and no professional development for the role. Read the PMI research on executive sponsor engagement before you pick yours, because the failure mode is almost never a bad sponsor.
It is a good one who has eleven other priorities.
Pick someone senior enough that their decision ends the conversation. A sponsor who has to go and ask somebody else is a message carrier, not a sponsor.
Customer project manager
Your partner has a project manager. You need one too, and not as a courtesy. The partner’s PM manages the partner’s team and the partner’s commercial exposure. Yours manages your organisation’s ability to feed that team with decisions, data and people.
They decide sequencing inside your business, who attends which workshop, and when an issue gets escalated to the sponsor. They produce the internal plan, the issue and decision log, the resource calendar and the weekly status that your own leadership reads rather than the one the partner writes.
If you cannot free up a person for this, you are asking your finance director to do it in the evenings. That works for about six weeks.
Process owners
One per major process area: order to cash, procure to pay, record to report, plan to produce, hire to retire, depending on scope. These are the people who own the business rule, not the software screen.
A process owner decides how the business will work in the new system. That includes deciding to stop doing something the old way. They produce the signed requirements for their area, the approved solution design, the approved chart of accounts and dimension structure for their part of the ledger, and a written list of the exceptions they are prepared to live with.
The single most common structural fault in ERP projects is appointing a process owner who does not have authority to change the process. You end up with a design nobody can sign, and a sponsor who has to arbitrate every detail.
Super users
Two to four per process area on a mid-sized project. Super users are the people who actually key transactions today and will key them in the new system. They sit under the process owner and they are the bridge between design and reality.
They decide nothing formally. They produce the things that decide everything: the real-world test cases, the edge cases the design missed, the training content in your own business language, and later the first line of internal support.
Choose super users on credibility, not availability. The person everyone already asks is the right person, which is inconveniently also the busiest person.
Data owner
Somebody has to be accountable for whether the data that lands in the new system is correct. Not the partner. You.
The data owner decides how much history moves, what “clean” means for each entity, which duplicate survives a merge, and when a data set is signed off as ready to load. They produce the cleansing rules, the reconciliation control totals, and the signed reconciliation pack after each trial load.
ISACA’s guidance on data ownership makes the point plainly: ambiguity about who is responsible for an organisation’s data raises the potential for legal, reputational and financial harm, and accountability has to be assigned explicitly rather than assumed.
The ISACA Journal article on data ownership is worth ten minutes if you are about to argue with a colleague about whose customer master it is. Our ERP data migration strategy guide covers what this person is signing off in detail.
Technical or IT lead
Your IT lead decides how the new system connects to everything else you run, who gets which security role, how identities and licences are provisioned, and what your network, printing and device estate has to do differently on day one.
They produce the integration inventory, the environment and access plan, the security role mapping, and the cutover tasks that belong to IT rather than to the partner. On a cloud ERP project their workload is lighter than it used to be and more concentrated: less infrastructure, much more integration and identity.
If you outsource IT, this role still belongs to a named person inside your business. Your managed service provider can do the work. They cannot own the decision.
Testing coordinator
Testing is the role most often left unfilled, and the one whose absence shows up latest. A testing coordinator decides what “tested” means, which defects block go-live and which do not, and when the user acceptance test is finished.
They produce the test script library, the defect log, the daily progress report and the UAT exit report the sponsor signs. This is not writing the scripts, which super users do, or fixing the defects, which the partner does.
It is making sure a hundred scripts across seven process areas actually get run by named people before the date. See our ERP user acceptance testing guide for the artefacts.
The honest weekly time commitment
These are Alphavima’s observed averages across mid-market implementations of roughly six to nine months. They are not a contractual commitment and they vary with scope. The point of publishing them is that most plans assume roughly half of these numbers, and half is where slippage starts.
| Role | Discovery and design | Build and configure | Test and train | Cutover and first month | Typical total commitment |
|---|---|---|---|---|---|
| Executive sponsor | 3 to 4 hrs/wk | 2 hrs/wk | 3 hrs/wk | 5 to 8 hrs/wk | Under 10 percent |
| Customer project manager | 4 to 5 days/wk | 4 days/wk | 5 days/wk | 5 days/wk | 80 to 100 percent |
| Process owner (each) | 2 to 3 days/wk | 1 to 2 days/wk | 3 days/wk | 3 to 4 days/wk | 40 to 60 percent |
| Super user (each) | 1 day/wk | 1 to 2 days/wk | 3 to 4 days/wk | 4 days/wk | 30 to 70 percent |
| Data owner | 2 days/wk | 3 to 4 days/wk | 3 days/wk | 4 to 5 days/wk | 50 to 80 percent |
| IT lead | 1 to 2 days/wk | 2 days/wk | 2 days/wk | 4 days/wk | 30 to 60 percent |
| Testing coordinator | 0.5 day/wk | 2 days/wk | 5 days/wk | 2 days/wk | 30 to 90 percent |
Two things to notice. The load is not flat, so a plan that books everyone at a constant 20 percent is wrong in both directions. And the two heaviest roles, project manager and data owner, are the two most often given to someone as an addition to a full existing job.
A RACI across the main deliverables
RACI stands for responsible, accountable, consulted and informed, and it is a form of responsibility assignment matrix. The rule that carries the whole model, as PMI sets it out, is that every deliverable has exactly one accountable name. Responsibility can be shared. Accountability cannot.
Copy this into your own plan and change the names. Key: A accountable, R responsible, C consulted, I informed.
| Deliverable | Sponsor | Cust PM | Process owner | Super user | Data owner | IT lead | Test lead | Partner |
|---|---|---|---|---|---|---|---|---|
| Signed requirements by process area | I | C | A | R | C | C | I | R |
| Solution design document | I | C | A | C | C | C | I | R |
| Chart of accounts and dimensions | C | I | A | C | C | I | I | R |
| Integration specifications | I | C | C | I | C | A | I | R |
| Security roles and permissions | I | C | C | I | C | A | C | R |
| Data cleansing rules and execution | I | C | C | R | A | C | I | C |
| Trial load and reconciliation sign-off | I | C | C | R | A | I | C | R |
| Test scripts | I | C | C | A | C | C | R | C |
| UAT execution and defect triage | I | C | C | R | C | C | A | R |
| Training delivery | I | C | C | R | I | I | I | A |
| Cutover runbook | I | A | C | C | C | R | C | R |
| Go or no-go decision | A | R | C | I | C | C | C | C |
| Hypercare triage | I | A | C | R | C | C | I | R |
Note where accountability moves. Design belongs to process owners. Data belongs to the data owner. Security and integration belong to IT. Only the go or no-go decision belongs to the sponsor, and it is the only row where it should.
Our ERP go-live readiness assessment is the evidence pack that row is based on.
The backfill question
Here is the conversation nobody has until week nine. Your best finance person is on the project four days a week. Who does their job?
There are four honest answers and one dishonest one.
| Option | What it costs | When it works |
|---|---|---|
| Backfill with a contractor | Three to six months of a temporary rate, plus two weeks of handover | Transactional roles: AP clerk, order entry, credit control |
| Redistribute across the team | Goodwill, and some overtime | Small, short overlaps of six to eight weeks |
| Defer non-critical work | A slower month-end, a delayed audit prep, a paused improvement project | Almost always available and almost never used |
| Reduce the person’s project allocation | Schedule risk, moved dates, or a design signed by someone with less authority | When the role is genuinely part-time, such as a second super user |
| Ask them to do both | Burnout, resignations, and defects found in production | Never |
The dishonest answer is the last one, and it is the default. It is also the reason the best person on the project is frequently the first person to leave after go-live.
A practical rule: backfill the transactional half of a role and protect the judgement half. Hire against the processing, keep the judgement, and put the freed time on the project. Budget for it explicitly in the business case, because an unbudgeted backfill is a backfill that never gets approved.
Not sure your side of the project is properly staffed?
Alphavima runs a short resourcing review against your scope and your date, and gives you a named-role structure with realistic hours you can take to your leadership team. Book a conversation and bring your current project plan.
Where your team meets the partner team
Most escalations are not caused by anyone failing. They are caused by two people each reasonably believing the other one owned something. The boundaries are predictable, so write them down before you reach them.
| Boundary | Customer owns | Partner owns | Where it usually goes wrong |
|---|---|---|---|
| Requirements | What the business needs | Whether the product can do it and at what cost | Requirements written as software features, so nobody can challenge them |
| Data | Content, correctness, cleansing decisions | Extraction tooling, field mapping, load, reconciliation reporting | Partner assumes clean data, customer assumes partner will clean it |
| Configuration | The business rule | The setting that implements it | Customer never sees the setting, so discovers the rule at UAT |
| Testing | Whether it works for the business | Whether it works as designed | Partner declares “as designed”, customer declares “unusable”, nobody declares a defect |
| Training | Who is trained and whether they are competent | Content, delivery, materials | Attendance recorded, competence never measured |
| Cutover | Business decisions, stopping and restarting operations | Technical sequence and timings | Nobody owns the moment between the last old transaction and the first new one |
| Post go-live | Triage, prioritisation, business workarounds | Fixes, root cause, product escalation | No agreed severity definitions, so everything is a priority one |
Give each boundary a named person on each side and say out loud, in a meeting, which of the two is accountable. In our experience, when two functions both claim the accountable seat, or both quietly duck it, the fix is not a tidier grid.
It is a decision the sponsor has to make, and it is much cheaper made early than argued out during hypercare.
Sizing the team for your project
For a 25 to 75 user implementation covering finance, sales, purchasing and inventory, a workable structure is one sponsor, one full-time project manager, three to four process owners, eight to twelve super users, one data owner, one IT lead and one testing coordinator.
That is roughly fifteen to twenty named people, of whom two or three are effectively full time.
Below about eight named people, the project is running on heroics. Above about thirty, you have a governance problem rather than a resourcing one, and you should be pushing decisions down rather than adding names.
If your list of names is shorter than your list of processes, that is the finding. Fix it before the design workshops start, not after. The phases this team works through are set out in our guide to ERP implementation phases, and what these people have to be trained on is covered in the ERP training plan.
Frequently asked questions
Who should be the executive sponsor on an ERP project?
Someone senior enough that their decision closes the question, with direct authority over the departments in scope. In most mid-market businesses that is the CFO, COO or managing director. The test is simple: if the sponsor has to check with someone else before approving a scope change, they are relaying decisions rather than making them, and every approval will take a week longer than the plan assumes.
How many super users does an ERP implementation need?
Two to four per major process area is a reasonable starting point for a 25 to 75 user implementation, which usually lands between eight and twelve people in total. Fewer than two per area leaves you exposed if one leaves or goes on holiday during UAT. More than four per area tends to dilute the role until nobody feels it is really theirs.
Can the same person be project manager and process owner?
On a very small project, occasionally. On anything with more than one process area, it is a false economy. The two roles conflict: a process owner advocates for their area and a project manager arbitrates between areas. Combining them means the loudest area wins, and it means one person becomes a single point of failure for both the plan and the design.
What does the customer project manager do that the partner's project manager does not?
The partner's project manager runs the partner's team, scope and commercials. Yours runs your organisation's ability to supply decisions, data and people on time. That means internal scheduling, chasing sign-offs, protecting the team's project time from operational pull, managing the backfill plan and briefing your own leadership. Nobody outside your business can do that work.
How do we handle the backfill if we cannot afford a contractor?
Split the role rather than the person. Identify the transactional part of the job that a temporary resource or a colleague could absorb, and the judgement part that cannot be handed over. Then deliberately defer discretionary work such as improvement projects, non-statutory reporting or system tidy-ups for the duration. The cost is real either way, so the choice is between paying it in cash or paying it in deferred work.
When should the ERP implementation team be assembled?
Before the first design workshop, and ideally before contract signature. Names, allocations and backfill plans should be agreed while you still have negotiating room and while the date is still movable. Assembling the team after kick-off means the first three weeks are spent discovering who is available rather than designing anything.
What happens to the team after go-live?
Super users become first-line support and the process owners become the owners of the system's ongoing configuration, not just its original design. The project manager role usually shrinks to a part-time system owner role within about three months. The mistake is dissolving the structure entirely at hypercare exit, because the questions do not stop, they just become invisible.